Job Activity Configuration Procedures
Adding or Removing Columns in the Job Activity Pane
To add or remove columns:
-
Click Operations >Job Activity on the Navigation pane to display the Job Activity pane.
-
Click View > Preferences on the main menu bar or right-click the Navigation pane and select Preferences from the context menu to display the Preferences dialog.
-
Click the Columns tab. By default, all columns are used.
To remove columns, clear the checkbox to the left of the column name.
To include columns, click the checkbox so that a black checkmark appears.
Adding a New Job or Group Occurrence to the Schedule
To add a new job or group occurrence:
-
Click Operations > Job Activity on the Navigation pane to display the Job Activity pane.
-
Right-click on the job or job group occurrence to add to the production schedule and select Insert Job into Schedule from the context menu or click the job or job group, and from the Activities main menu, select Insert Job Into Schedule.
-
Click Yes at the confirmation prompt.
Another occurrence of the selected job or job group is added to the current day’s production schedule irrespective of its calendar dates, if any. If the job is defined to repeat, only one occurrence of the job enters the schedule.
Note: You can insert a job into the schedule using the Insert Job into Schedule option if the Allow unscheduled option is selected in the Job Definition dialog > Options tab.
Adding New Job or Group Occurrences in Batch to the Schedule
To add two or more new job or group occurrences:
-
Click Operations > Job Activity on the Navigation pane to display the Job Activity pane.
-
Click the jobs or job groups and right click on the job or job group occurrences.
-
Choose Insert Jobs into Schedule as a Batch from the context menu or select the job and job group occurrences and select Insert Jobs into Schedule as a Batch from the Activities main menu.
-
Click Yes at the confirmation prompt.
Another occurrence of the selected jobs or job groups is added to the current day’s production schedule irrespective of the calendar dates, if any. If the jobs are defined to repeat, only one occurrence of the jobs enter the schedule.
Note: You can insert the selected jobs and job groups into the schedule using the Insert Jobs into Schedule as a Batch option if the Allow unscheduled option is selected in the Options tab of the Job Definition dialog or Job Group Definition dialog.
Adjusting Column Widths in the Job Activity Pane
To adjust a column’s width:
-
Place the cursor on the right vertical border of the column heading. The mouse pointer turns into the separator icon.
-
Hold down the left mouse button and resize the width.
Deleting Jobs or Groups from the Production Schedule
To remove jobs that have not yet launched from the production schedule:
-
Click Operations > Job Activity on the Navigation pane to display the Job Activity pane.
-
Right-click the job or job group occurrence to remove, and from the context menu select Remove Job(s) from Schedule. In the resulting confirmation dialog, select Yes if you only want to delete the selected job occurrence. If you wish to delete all future scheduled occurrences of the job, select the All option.
You can select multiple jobs or job groups simultaneously.
-
To select more than one job or job group that are adjacent to each other, hold down the Shift key and select the first and last jobs.
-
To select more than one job or job group that are not adjacent to each other, hold down the Control key while selecting the desired job occurrences.
-
-
Click Yes at the confirmation prompt.
Remove Job(s) from Schedule will remove any pre-launch job occurrence from the schedule, for any date. Only the job occurrence you select is removed. If a job group occurrence is selected, all of the group’s child jobs are removed.
Filtering Jobs in the Job Activity Pane Based on Job Status
To filter a job:
-
Click Operations > Job Activity on the Navigation pane to display the Job Activity pane.
-
Click Filter on the TA toolbar or right-click the Navigation pane and select Filter from the context menu to display the Job Filter dialog.
The statuses that are presently displayed are the ones with a check mark.
-
Select the agent, owner and job statuses to view.
Moving to Different Dates and Times in the Job Activity Pane
You can view job occurrences for past, present or future days. Each job’s retention history value in its job definition determines how far back you can see its job occurrences. The Future Days value in the System Configuration dialog determines how far you can see into the future.
Note: When you are viewing the current day in the Job Activity pane, you may also see jobs from previous dates if those jobs have not yet completed.
To move to different dates and times:
-
Click Operations > Job Activity on the Navigation pane to display the Job Activity pane.
-
To move backward one day in the production schedule, right-click in the Job Activity pane and select Prior Day from the context menu.
-
To move forward one day in the production schedule, right-click in the Job Activity pane and select Next Day from the context menu.
-
To move to today’s date and time, right-click the Job Activity pane and select Goto Now from the context menu.
-
To move to a job’s graphical start location, right-click the job’s record and select Goto Job Time from the context menu to display the job’s start time.
-
Pausing the Production Schedule
You can pause and then resume the production schedule at any time. You can also pause and resume job launching without having any affect on scheduling.
When you pause a production schedule, the Master service is stopped and waiting jobs are prevented from running, even if their dependencies are met. Jobs that are already in Active status will continue to run on their respective agents; however, their updated status (for example, Completed Normally) will not be displayed in the Job Activity pane until the Master service is restarted.
When you pause job launching, jobs can still be scheduled and calendars compiled, but jobs will not actually launch until job launching is resumed.
To pause the production schedule or job launching:
-
Click Operations > Job Activity > on the Navigation pane to display the Job Activity pane.
-
Choose Pause Scheduler or Pause Job Launching on the Activities main menu.
Rearranging Columns in the Job Activity Pane
To rearrange columns:
-
Click Operations > Job Activity on the Navigation pane to display the Job Activity pane.
-
Click the View main menu and choose Preferences or right-click the Navigation pane and select Preferences from the context menu to display the Preferences dialog.
-
Click the Columns tab.
-
Click the column and click the up or down arrows to arrange the titles into the desired order.
Recreating the Production Schedule
To recreate the production schedule:
-
Click Operations > Job Activity on the Navigation pane to display the Job Activity pane.
-
Click Create Schedule on the Activities menu to display the Create Schedule dialog.
-
Choose the date range for which to create the schedule.
If you want repeating jobs with no time window to start immediately, rather than after midnight, select the For today’s repeating jobs with no time window, start repeating ASAP option.
TA searches for all qualified jobs to add to the production schedule for the selected dates.
Note: All job occurrences that were added manually and all records of jobs that ran will be lost. Furthermore, the Create Schedule recreates the schedule at the time you issue the command. This means that jobs whose dependencies have not been met can qualify to run immediately. Use this command with caution.
Refreshing the Job Activity Pane
To refresh the pane:
-
Click Operations > Job Activity on the Navigation pane to display the Job Activity pane.
-
Click Refresh on the View main menu.
Resuming the Production Schedule or Job Launching
To resume the production schedule or job launching:
-
Click Operations > Job Activity on the Navigation pane to display the Job Activity pane.
-
Choose Resume Scheduler or Resume Job Launching on the Activities main menu.
Saving a Job’s Output on the Master
You can view the output of a job after the job finishes running. In order to view the output of a job from the Job Activity pane, you must save the output for the job on the Master (this is the default).
To save a job’s output on the Master:
-
Click Definitions > Jobs on the Navigation pane to display the Jobs pane.
-
Click the job for which to save output.
-
Click Edit to display the Job Definition dialog.
-
Click the Options tab.
-
Click Append or Replace on the Save Output option.
-
Click OK. The next time the job completes, you can view its output from the Job Details dialog.
Selecting or Removing All Job Filters in the Job Activity Pane
To select or remove all job filters:
-
Click Operations > Job Activity on the Navigation pane to display the Job Activity pane.
-
Click Filter on the TA toolbar or right-click the Navigation pane and select Filter from the context menu to display the Job Filter dialog.
-
Right-click in the Statuses section and select Check All or Uncheck All from the context menu.
Setting the Completion Status of a Job
Note: You should only set the completion status of jobs that have already finished running. Setting completion status of a job that is still active, may adversely affect job activity.
To set the completion status:
-
Click Operations > Job Activity on the Navigation pane to display the Job Activity pane.
-
Click the job on which to perform job control.
-
Right-click the job to open the Job Activity context menu.
-
Click the Job Control submenu and choose Set and from the Set submenu, select the desired job completion status.
Note: When job completion statuses are changed in this way, an asterisk appears to the right of it, for example, Completed Normally*.
Sorting Jobs in the Job Activity Pane Using Column Headers
You can sort the job occurrences displayed in the Job Activity pane by two different sorting criteria. You can sort on a primary criteria and in turn, organize the primary sort by secondary criteria. The sorts are done by column header in either alphabetical or numerical order depending on the type of data contained in the column.
To sort a job using a column header:
-
Click Operations > Job Activity on the Navigation pane to display the Job Activity pane.
-
Click the column header to select it for a primary sort. The jobs sort alphabetically (in text data) or numerically (if numerical data). A single arrow displays beside the column header to denote the primary sort.
If you click the header more than once, the sort order toggles back and forth from ascending to descending order.
-
To perform a secondary sort, hold down the ALT key while clicking the column header. The secondary sort displays a double arrow in the column header.
Example: Click the Name column heading. The items in the column are alphabetized from a to z (because the column contains alphabetical data). Clicking again reverses the order z to a. Click the Time column header while holding down the ALT key and the jobs remain in alphabetical order but are now organized also by numerical order (since this column contains numerical data). Now the jobs are arranged in alphabetical order and each numerical segment is organized from earliest time to latest time. Clicking again on the secondary sort column while holding down the ALT key reverses the secondary sort to latest time to earliest time.
If you click the header more than once, the sort order toggles back and forth from ascending to descending order.
Sorting Jobs Using the Job Filter Dialog
To sort jobs using the Job Filter dialog:
-
Click Operations > Job Activity on the Navigation pane to display the Job Activity pane.
-
Click Filter on the TA toolbar or right-click the Navigation pane and select Filter from the context menu to display the Job Filter dialog.
-
Checking or clearing the options for status or hours enables you to sort jobs using those criteria. You can also sort using other criteria listed including by job name, by agent, by queue, by command, etc.
Note: The Job Filter dialog includes filter options that affect sorting. For example, if you want to sort by the status column, and some statuses have been filtered out, those statuses will not be used for sorting.
Note: When a Status column is clicked for sorting within the Job Activity pane, the order is defined by the settings on the Job Status Order tab in the System Configuration dialog.
Stopping or Starting Jobs in the Job Activity Pane
To stop or start a job:
-
Click Operations > Job Activity on the Navigation pane to display the Job Activity pane.
-
Click the job on which to perform job control.
-
Right-click the job to display the Job Activity context menu
-
Click the Job Control submenu and choose one of these job control options:
-
Click Override to nullify a job’s dependencies. The job enters a queue and becomes active. Override ignores all dependencies and launches the job immediately.
-
Click Hold/Stop to stop a job from running or to keep a job from launching. The job enters the Held or Stopped status. If the job cannot be held or stopped, you cannot select this menu item.
Note: Windows jobs cannot be suspended, therefore this menu item is unavailable for active Windows jobs.
-
Click Release/Resume to release a held job, or a job waiting for operator release, or to start a stopped job. The job enters the Active or Waiting On Dependencies status. If the job can’t be released or resumed, you won’t be able to select this menu item.
-
Click Cancel/Abort to cancel a job before running or to abort a job while running (Cancelled jobs cannot be rerun). The job enters the Cancelled or Aborted status. If the job cannot be cancelled or aborted, you cannot select this menu item.
-
Click Cancel/Abort All to cancel all occurrences of a job before running or to abort all occurrences of a job while running. All occurrences of the same job enter the Cancelled or Aborted status.
-
Click Revert to Scheduled to revert a cancelled job, a terminated job, or a job with the Cancel Pending status. The job enters the Active or Waiting On Dependencies status, if the Master is in production day. If the Master is not in production day, the job enters the Scheduled status. This option is disabled for jobs that cannot be reverted.
-
Click Revert group only to Scheduled to revert a cancelled job group only. The job group enters the Active or Waiting On Dependencies status, if the Master is in production day. If the Master is not in production day, the job group enters the Scheduled status and the status of the children cannot be changed. This option is disabled for job groups that cannot be reverted.
-
Click Revert group and children to Scheduled to revert a cancelled job group and its children. The job group and its children enter the Active or Waiting On Dependencies status, if the Master is in production day. If the Master is not in production day, the job group enters the Scheduled status. This option is disabled for job groups that cannot be reverted.
-
Click Rerun to rerun a job. The job re-enters the schedule and is re-executed with the same job ID number. A new occurrence ID is not created. If the job can’t be rerun, you won’t be able to select this menu item.
-
Note: When a group that requires resources has completed, it releases its resources. Rerunning a child of that group will not cause the group to try to reclaim resources.
Controlling Child Jobs from the Job Activity Pane
To control a child job:
-
Click Operations > Job Activity on the Navigation pane to display the Job Activity pane.
-
Click the job group on which you want to perform child job control.
-
Right-click the job group to display the Job Activity context menu.
-
Click the Child Job Control submenu and choose one of these job control options:
-
Release All Children Waiting on Operator – Changes the status of all the children of the selected job group from Waiting On Operator to Active (with an intermediate Scheduled state).
-
Revert All Cancelled Children to Scheduled – Changes the status of all the children of the selected job group from Cancelled to Active or Waiting On Dependencies, if the Master is in production day. If the Master is not in production day, changes the status of the selected job group’s children to Scheduled.
-
Rerun All Child Jobs With Status – Changes the status of all the child jobs of the selected job group to Active or Waiting On Dependencies. The selected option can affect all other jobs dependent on that job or job group. A new instance ID of the job is not created.
You can select one of these options:
Completed Abnormally
Error Occurred
Orphaned
Note: When a group that requires resources has completed, it releases its resources. Rerunning a child of that group will not cause the group to try to reclaim resources.
-